Moses-Adirondack Smart Path Reliability Project
Smart Path: Rebuilding an aging transmission line
Work has resumed on the Smart Path project, a vital transmission infrastructure project to rebuild and strengthen the Moses-Adirondack transmission lines. In coordination with New York State and other regional partners, NYPA identified a number of essential generation and transmission projects and associated construction, including the Smart Path project, that can safely continue using additional precautions against the spread of the COVID virus.
Through an Incident Command Structure, NYPA will continue to monitor the pandemic and make adjustments to these precautions as necessary.
About the Smart Path project:
NYPA is rebuilding its 86-mile-long Moses-Adirondack transmission line. Though consistently well-maintained, the line is over 70 years old and has exceeded its service life. Rebuilding the line will lead to long-term benefits and support future upgrades in voltage, which would allow for greater transmission of energy from renewable sources developed in Northern New York.
Reforming the Energy Vision: Building a cleaner, more resilient, and affordable energy system for all New Yorkers. #REV4NY
Rebuilding NYPA's Moses-Adirondack transmission lines: 86 miles long, the line runs from the switchyard at NYPA’s St. Lawrence-Franklin D. Roosevelt Power Project in Massena to the Adirondack Substation in Croghan.
The lines were built in 1942 and have exceeded their service life. The MA1&2 lines are essential for system reliability and system restoration (blackstart). Plan includes the removal of the old wooden H-frame structures and a rebuild with modern steel monopole structures.
Licensing and engineering studies began in 2015 and will continue through 2019.
Schedule (subject to change):
2020: Start of Construction
2023: Completion of Construction
The Project will be required to obtain permits and approvals from the following agencies:
- Federal Aviation Administration:
- New York State Public Service Commission:
- PSC Case # 18-T-0207
- Approved Environmental Management & Construction Plan for Segment 1
- Approved Article VII
- US Army Corps of Engineers:
- New York State Department of Environmental Conservation
Documents related to these regulatory approvals will be posted once completed.
June 20, 2023: Governor Hochul Announces Completion of North Country's Smart Path 78-Mile Clean Energy Transmission Project | Governor Kathy Hochul
August 11, 2022: Governor Hochul Announce Two-Thirds Completion Milestone for "Smart Path" Clean Energy Transmission Line in the North Country
November 24, 2020: NYPA Reaches First Milestone in the Rebuild of Major North-South Transmission Artery
February 6, 2020: PSC Greenlights 1st Phase of NYPA’s Smart Path Transmission Project
February 3, 2020: Governor Cuomo Announces $341 Million in Funding to Rebuild Critical Power Transmission Link in the North Country
November 14, 2019: PSC Approves Rebuild of Moses-Adirondack Transmission Line
October 10, 2018: New York Power Authority Trustees Approve $124 Million for Rebuild of Major North-South Transmission Artery
April 5, 2018: NYPA Files Formal Application for Rebuild of Major North-South Power Transmission Artery
February 16, 2018: NYPA to Hold Informational Meetings on Smart Path - The Planned Rebuild of NYPA's Moses Adirondack Transmission Lines
October 10, 2017: New York Power Authority Trustees Approve First Phase Funding for Rebuild of Major North-South Transmission Artery
July 21, 2017: Governor Cuomo Announces Plan to Rebuild 78 Miles of Power Transmission Infrastructure in the North Country
If you have questions about the Moses-Adirondack Smart Path Reliability Project, please contact us:
Jeff Farrell
Real Estate Administrator
Phone: 315-764-6837
Jeffrey.Farrell@nypa.gov
Karen White
Manager, Community Relations
New York Power Authority
Phone: 315-764-6863
Karen.White@nypa.gov
Or call: 866-697-8758
An updated construction schedule will be posted soon
Smart Path: Rebuilding an aging transmission line
Work has resumed on the Smart Path project, a vital transmission infrastructure project to rebuild and strengthen the Moses-Adirondack transmission lines. In coordination with New York State and other regional partners, NYPA identified a number of essential generation and transmission projects and associated construction, including the Smart Path project, that can safely continue using additional precautions against the spread of the COVID virus.
Through an Incident Command Structure, NYPA will continue to monitor the pandemic and make adjustments to these precautions as necessary.
About the Smart Path project:
NYPA is rebuilding its 86-mile-long Moses-Adirondack transmission line. Though consistently well-maintained, the line is over 70 years old and has exceeded its service life. Rebuilding the line will lead to long-term benefits and support future upgrades in voltage, which would allow for greater transmission of energy from renewable sources developed in Northern New York.