NYPA Press Release
News Published:11/20/2026
For Immediate Release
November 20, 2026
Contact: Marykate Guilfoyle, marykate.guilfoyle@nytransco.com
PROPEL NY ENERGY ADVANCES TOWARDS CONSTRUCTION FOLLOWING APPROVAL OF PHASE 1 AND 2 CONSTRUCTION PLANS
Project Announces Key Suppliers and Contractors to Support Initial Construction Activities
View Educational Animated Terrestrial Construction VideoHere
Garden City, N.Y. – New York Transco (NY Transco) and the New York Power Authority (NYPA) today announced the selection of contractors to perform initial Propel NY Energy work, as well as key equipment suppliers following state approval of two construction plans. Propel NY Energy is a 90-mile underground and submarine electric transmission project spanning parts of Long Island, Queens, the Bronx, and Westchester County designed to improve the reliability, resiliency, and capacity of the New York State grid.
On Nov. 19, 2026, the New York State Public Service Commission (PSC) approved the project’s Phase 1 and Phase 2Environmental Management and Construction Plans (EM&CPs), after several months of public comment and regulatory reviews. These approvals come a day after the New York Independent System Operator, the state’s grid operator, released its2026 Reliability Needs Assessment stating that Propel NY will provide significant benefits to statewide resource adequacy and strengthen reliability between Long Island, New York City and the rest of the state.
EM&CPs are a required part of the state permitting process todetail how the project will be built in compliance with all applicable laws and the conditions that resulted from the September 17 PSC permit approval. Due to the nature and scale of the Propel NY project, multiple EM&CPs will cover different regions and scopes of work. The companies selected through the procurement process for Phase 1 and Phase 2 construction activities bring extensive experience delivering complex infrastructure projects and a strong commitment to employing a highly skilled, union workforce. Additional contractors for other phases of work will be announced upon the conclusion of the procurement process.
Throughout an anticipated four-year construction period and across all phases of work, the project will support an estimated 2,000 jobs annually, while boosting the local and regional economy by an estimated $2.4 billion.
“Propel NY Energy will deliver a more reliable energy future for New York while creating meaningful economic opportunities for communities along the project route. The recent construction plan approvals and the contract awards to our construction partners underscore project maturity and readiness for construction,” said Joris Veldhoven, President, New York Transco. “We’re pairing best‑in‑class companies with skilled union labor to responsibly build infrastructure that safeguards communities and the environment, strengthens the grid, and supports family-sustaining jobs.”
“Propel NY Energy is an important infrastructure project that will increase energy capacity and access to clean, reliable power and improve resiliency for the electric system, specifically during high demand and severe weather incidents,” said Justin E. Driscoll, President and CEO, New York Power Authority. “To deliver this major grid modernization project, NYPA along with our development partner NY Transco, are enlisting the expertise and experience of a stable of union laborers and qualified contractors. Our team is working closely with communities along the project route and responsible contractors to ensure the project proceeds in a safe and timely manner, to deliver the project’s benefits to New Yorkers.”
EM&CP Phase 1
EM&CP Phase 1 focuses on vegetation management at the Long Island substations. The plan was initially filed on June 22, 2026, agency and public comments were incorporated, and an updated plan was refiled on October 9, 2026.
Burns & McDonnell was selected to serve as the prime contractor for the project's three new Long Island substations that will be built on existing utility-owned property adjacent to existing stations -- Shore Road, Ruland Road, and Barrett.Haugland Group andHitachi Energy will work alongside Burns & McDonnell as key subcontractors. Additionally, the project proactively procured critical long-lead equipment fromSGB-SMIT Group and Hitachi to support timely execution of key project milestones.
EM&CP Phase 2
EM&CP Phase 2outlines construction activities for specific portions of the project involving horizontal directional drilling (HDD) at the two landfall locations to support future submarine cable installation. The plan was initially filed on July 10, 2026, agency and public comments were incorporated, and an updated plan was refiled on October 16, 2026.
TheCrossing Group has been selected to execute trenchless crossings (HDD) for the landfall of the submarine crossing from New Rochelle to Glen Head. The Crossing Group is partnered withHallen Integrated Construction Services (HICS) to complete the work.
Transmission Cable
The contractors selected for supplying the terrestrial cableareLS Cable & System andTaihan, both of which have extensive experience delivering large-scale transmission projects in the U.S. and around the globe. These companies will be working with local contractors to install and splice the cable. LS Cable & System will also supply and install the submarine cable.
Pending additional approvals, Propel NY Energy anticipates beginning construction early next yearwith site work at discrete areas along the route. More active construction is anticipated to begin in mid-2027. Construction will be executed in segments and phases, with multiple crews operating at various locations simultaneously to deliver the project in 2030.
To maintain the ongoing commitment to community engagement, the next quarterly project webinar will be held on Dec. 15 at 6 p.m., providing stakeholders with an opportunity to receive project updates and submit questions directly to the team. The webinar will also detail several new public outreach tools, including a redesigned website to track future construction progress with aninteractive project map, a new animated construction educationalvideo, a soon to be launched 24/7 staffed inquiry hotline, and an online inquiry form to help community members easily access information and stay connected throughout construction.
Ben Greek, Vice President, Global Director Power Delivery Construction, Burns & McDonnell said:“Propel NY Energy is the type of complex, consequential infrastructure project that brings together the full strength of our integrated engineering, procurement and construction capabilities. Burns & McDonnell is proud to team with New York Transco and the New York Power Authority in delivering safe, reliable and resilient substation infrastructure that will help modernize New York’s electric grid and accommodate the state’s evolving energy needs.”
Billy Haugland II, Chief Executive Officer, Haugland Group LLC said: “Propel is a generational investment in Long Island's energy infrastructure, and we're proud that investment is being put to work locally— through New York companies, union tradespeople, and communities. Construction is temporary, and once complete, the infrastructure will be part of our daily lives— delivering greater reliability, economic opportunity and capacity for Long Island. As a local, family-owned union contractor, Haugland is proud to be part of building a more resilient future for our region.”
Spencer Hoyda, President, The Crossing Group, said:“The Crossing Group is proud to lead the marine trenchless scope for Propel NY Energy. This technically complex project requires close coordination across drilling, marine and civil construction, with a strong focus on safety and minimizing community disruption. Our team will bring extensive North American trenchless experience, supported by local construction partner Hallen Integrated Construction Services and its skilled union workforce. We look forward to working with New York Transco, NYPA and the broader project team to deliver this important infrastructure and help strengthen New York’s electric grid.”
Pascale Ambrosio Jr, President, Hallen Integrated Construction Services said: “The Propel NY Energy project is an important investment in the reliability and resiliency of New York’s electric transmission system. Hallen Integrated Construction Services is proud to support NY Transco and NYPA as a local contractor with specialized construction experience and the backing of an extensive network of resources. We are committed to delivering our work safely, responsibly, efficiently and cost-effectively while coordinating closely with the project team and communities along the project route.”
Kye ho Jon, President, LS Cable Systems America said:“LS Cable Systems America, Inc. is proud to support the Propel NY Energy project through the supply and installation of 345kV high-voltage cable systems, including both the project’s submarine cable segment and the project’s underground segments. With extensive experience in high-voltage transmission cable systems, we are committed to safe, reliable, and collaborative delivery with NYPA, New York Transco, and our project partners—helping strengthen New York’s energy reliability and resiliency."
Kyungsoo Choi, President, Taihan Electric USA said: “A stable and resilient power grid is essential infrastructure that supports the sustainable growth of cities and industries. We are honored to contribute Taihan’s technology and expertise to this critical project to modernize New York’s power grid and prepare for future electricity demand. Building on our proven extra-high-voltage cable system technology in North America and extensive experience delivering transmission grid projects worldwide, we will work closely with NY Transco and NYPA to help build stable and reliable power infrastructure. Through this project, we will further strengthen our position as a strategic partner in advancing power grid modernization across North America.”