|
Executive Speeches

Excerpts from remarks of Roger B. Kelley,
president and chief executive officer of the New York Power Authority,
at the Independent Power Producers of New York’s Annual Membership
Meeting and Fall Conference, Saratoga Springs, New York.
September 25, 2007
I’m very pleased to have this opportunity to share some
thoughts with you at a critical time for the electric power industry,
for the members of IPPNY and for the Power Authority.
Together, our organizations account for virtually all
of the electricity that’s produced in New York State. And much of the
power NYPA uses to serve customers ranging from governmental entities in
downstate New York to businesses throughout the state is generated by
the companies represented here tonight.
Beyond that, we all have a part in addressing some of
the most imposing energy problems in this state’s history.
The fact is that—with the encouraging exception of new
wind generation upstate—the additional power plants and transmission
lines that New York will need to meet its future energy requirements
have not yet been built.
There are, of course, some very clear explanations for
this.
The absence of a power plant siting law to replace the
Article Ten legislation that expired at the end of 2002 is a major
concern. I know there are significant differences of opinion, but I
hope the policymakers in Albany will arrive at a resolution that leads
to enactment of a new siting law.
Still other obstacles have arisen in the years since
Article Ten expired.
We’re seeing a steep rise in construction costs for
power plants and transmission lines because of huge increases in demand
for raw materials, labor and other items. Longer manufacturing lead
times are drawing out project construction—increasing debt costs. This
was underscored in a recent report for an affiliate of the Edison
Electric Institute which found that prices for steam generating plants,
transmission projects and distribution equipment went up by 25 to 35
percent between 2004 and this year.
In this climate, there is a need for greater reliance
on long-term contracts or long-term markets to ensure potential
investors that debt will be repaid. The absence of such mechanisms has
impeded access to the credit markets.
The New York Independent System Operator predicted
earlier this year that substantial infrastructure additions—in the form
of generation, transmission or demand resources—will be needed by 2011
to ensure reliable service in Southeastern New York, and beginning in
2012 for the state as a whole. Those lead times are already very tight
for licensing and construction of new facilities.
As a follow-up, the ISO last week issued its 2007
Comprehensive Reliability Plan, which found that market-based generation
and transmission proposals, along with plans by the regulated
transmission owners, would—if implemented—meet or exceed reliability
requirements through 2016. But the report also cited a number of risks
and uncertainties that could affect these projects.
Bear in mind, too, that the ISO forecasts are based
strictly on reliability needs. They don’t consider the potential
benefits of new capacity in encouraging competition and reducing costs
to consumers, in providing fuel diversity and in cleaning the air by
permitting retirement of older, less-efficient units. These are all
essential considerations as we plan for the future.
Against this backdrop, I’d like to talk to you about
how I see the New York Power Authority’s role in meeting the state’s
energy requirements.
First, let me say that Governor Spitzer has told me
that he wants to use the Power Authority to the greatest possible extent
to benefit the people of this state.
This means that NYPA will move aggressively to help
meet the governor’s ambitious “15 by 15” target of cutting the state’s
energy use by 15 percent below the forecasted level by 2015.
It means we will figure prominently in efforts to
achieve the goals of the Renewable Portfolio Standard and the Regional
Greenhouse Gas Initiative.
And it means we will again focus—where appropriate—on
our traditional role of electric power infrastructure development.
We continue to view the private sector as the primary
provider of new generation—and new transmission. But we will do what is
necessary if needs are not being met.
Nowhere are such needs more acute than in New York
City, where a series of power-supply agreements call for NYPA to serve
the city government and other large public entities through 2017. A
number of factors could—as soon as 2010—threaten our ability to provide
reliable, economical service.
Under two agreements concluded a number of years ago,
we’ll be required to close our 885-megawatt Charles Poletti Power
Project in Queens on January 31, 2010, and—by sometime next year—we
might have to shut down two combustion turbines we installed in that
borough in 2001. Together, the loss of Poletti and the smaller plants
would deprive us of 964 megawatts of much-needed capacity within the
city. Already, under the Poletti agreement, we’ve had to limit the
plant’s capacity factor.
In light of all this, the Authority in 2005 issued a
request for proposals seeking 500 megawatts that would help us meet our
in-city capacity requirements.
The winning bidders were FPL Energy and Hudson
Transmission Partners. FPL would obtain the power from a plant operated
in Central New Jersey by another independent power producer—AES. It
would ultimately be carried into the city on a new 345-kilovolt
transmission line to be built under the Hudson River by Hudson
Transmission Partners.
The Authority views this capacity as a vital new asset,
and we’re working with Hudson Transmission and PJM to resolve
significant interconnection cost issues on the New Jersey side of the
line. We’re hopeful these will be settled. But—given the time required
to do so—it’s now clear that the line won’t be in service before the
first quarter of 2011—rather than in the summer of 2010, as we
originally anticipated. This has only heightened our concerns about the
outlook for New York City.
As of now, we project that a tight capacity market—made
significantly tighter by a Poletti shutdown—could conservatively
increase annual costs to our governmental customers in the city by $80
million to $100 million in the 2010-2011 period. And that’s without
considering the impact of a pending increase in Con Edison’s delivery
rates.
Looking further ahead, it’s clear that—even if all goes
smoothly with the Hudson Transmission project—still more capacity will
be required to meet the governmental customers’ long-term needs.
We’ve been discussing the overall situation with city
officials and the other customers and have recommended to them that they
consider having us issue another request for proposals for in-city
capacity.
We intend to issue a two-phase RFP—with the
“fast-track” first phase seeking proposals for 500 megawatts of capacity
that could be available by the summer of 2010. These would essentially
be limited to projects that are already well into engineering, siting
and permitting. And, as those of you who know me are aware, I fully
understand the dynamics of the market and will ensure that there will be
timely review of the RFP.
The second phase would involve proposals that would
take more time to develop and submit, and that would have more-flexible
in-service dates.
The Power Authority is considering—as one
option—building its own power plant—at the Poletti site or elsewhere in
the city. Other approaches could include construction by a private
entity, a repowering of Poletti, purchases from the private sector or a
“build-buy” combination. Depending on the supply outlook, we will look
at the possibility of building or purchasing capacity to meet citywide
needs—not just those of our customers.
Our recommendations to our customers and our trustees
will be based on the results of each phase of the RFP—on what we view as
the most favorable overall outcomes for the customers and the city.
The Power Authority recognizes the skill and experience
that companies like yours could bring to a power plant construction
project. We would welcome—and carefully consider—proposals for a
public-private partnership.
Under certain scenarios, for example, a successful
bidder could design, build or operate the plant for us. There could
also be an arrangement in which the Authority and a private entity would
share ownership of a new plant, with each entitled to a portion of the
output. Under some of these approaches, costs to NYPA’s customers could
be lowered by taking advantage of our tax-exempt financing.
I’m well aware that potential construction by NYPA—on
its own or in a partnership—represents a significant change from the
four supply RFPs we’ve issued since 2001. These entailed only power
purchases or financial arrangements with other parties. But I believe
we must explore all possibilities—in cooperation with our customers.
We’re also considering how to proceed in response to
the recent Public Service Commission order approving the National
Grid-KeySpan merger and requiring—among other conditions—the sale of
KeySpan’s 2,450-megawatt Ravenswood plant in New York City. I know many
of you were delighted that the sale was required—and somewhat less
pleased that the Power Authority will be allowed to bid on the plant.
We were surprised ourselves that the PSC included us.
At this point, we’re evaluating the merits of Power Authority
involvement in the bidding process. As with our own RFP, we’ll base our
decision on the needs of our customers and the city.
Let me assure you that the Power Authority remains
firmly committed to viable competitive power markets in New York State.
The goal must be to strengthen these markets and to do everything
possible to encourage private-sector investment in the infrastructure
that we need.
To this end, we believe that establishment of an
effective ISO forward capacity market—at least in New York City—deserves
serious consideration. The current six-month capacity market creates
considerable uncertainty that can only inhibit investment in new power
plants.
We also think the PSC should continue to look carefully
at encouraging the state’s investor-owned utilities to enter into
long-term power supply agreements with independent power producers as a
backstop to the competitive markets.
We’re participating in the commission’s proceeding on
this issue and have stated that we believe such contracts could
facilitate financing for new or repowered generation, as well as
transmission improvements and energy efficiency and renewable energy
projects. We’ve also demonstrated our support for this approach through
the various RFPs I mentioned earlier.
There are, however, difficult issues that have to be
resolved with respect to utility contracts, including cost recovery in
the IOU rates; potential effects on retail competition; and—as you well
know—possible impacts on capacity prices paid to existing generators.
Besides encouraging the construction of new power
plants, we must focus on improvements to the state’s transmission
system. This has become even more essential since the U.S. Department
of Energy included New York in one of the two National Interest Electric
Transmission Corridors it designated under the 2005 federal Energy
Policy Act. If we are unable to come up with our own transmission
solutions, there is a possibility that the federal government will do it
for us.
Of course, new transmission under certain circumstances
can reduce or eliminate the need for new generation—and the reverse is
also true. The Power Authority’s preference is for market-based
solutions that provide the greatest benefits in terms of reliability and
economics—and we hope an economic planning process now being developed
by the ISO will produce such solutions. However, we also recognize that
regulatory backstop initiatives by transmission owners may be required
to meet reliability needs in the absence of construction by independent
developers.
As with generation, the Power Authority cannot rule out
a possible future role in construction of new transmission. But our
current focus is on rigorously maintaining our existing system and on
identifying possible opportunities to strengthen it.
At the moment, we’re involved in an unusual
collaborative effort—known as the Tri-Lakes Reliability Project—to help
resolve longstanding power delivery problems in the Adirondack Park.
We’re working with National Grid and our municipal
system customers in Lake Placid and Tupper Lake to build a 46-kilovolt
power line that’s scheduled for completion on time for the 2008-09 peak
winter period.
NYPA obtained the regulatory approvals for the line and
is providing the financing. We’ll own the line until the start of
2012—when National Grid will buy it from us. They’ll also be
responsible for operation and maintenance. And we’re cooperating with
the two municipal systems to promote energy efficiency and clean energy
technologies in their service territories.
While on the subject of clean energy, I’d like to
briefly mention two other matters that may be of interest to you.
I was honored to be appointed to the New York State
Renewable Energy Task Force, chaired by Lieutenant Governor Paterson.
The group—which began meeting in late June—includes 16 representatives
from state and local government, the private sector and the
environmental and academic communities. It’s making steady progress in
its efforts to identify means of expanding the state’s use of renewable
energy and alternative fuels while also advancing energy efficiency.
Just this afternoon, the lieutenant governor was
briefed on the major recommendations in four subcommittee reports. The
process of refining those proposals will continue.
The task force’s recommendations will complement the
Renewable Portfolio Standard—as well as the Regional Greenhouse Gas
Initiative and the governor’s 15 by 15 program—in combating global
warming and reducing our dependence on expensive and potentially
unreliable energy sources. They could also open opportunities for you
in the renewable energy field.
Meanwhile, the Power Authority is working diligently
with one of your members—NRG Energy—toward possible construction of an
advanced clean-coal power plant at NRG’s Huntley station in Western New
York. Some of you may recall that the Authority conditionally awarded a
power-purchase contract to NRG last December under which we’d obtain up
to 600 megawatts from the integrated gasification combined-cycle plant.
Through the “Strategic Alliance” that we’ve formed with
NRG, we’re trying to identify measures to bring down the cost of the
plant—and the power—and to provide for carbon dioxide capture and
sequestration.
These related issues—cost and sequestration—bear on
development of clean-coal plants throughout the nation, and I think it’s
fitting that NYPA and NRG are cooperating in a significant initiative to
resolve them.
I say that because I believe it’s essential for the
Power Authority and New York’s independent power producers to join
forces wherever possible to take on major energy and environmental
challenges.
As I noted at the start, we’re already doing so in a
number of ways—and I’m confident we can build on this foundation.
I recognize that there inevitably will be times when
our interests diverge—it was, after all, not too long ago that I was
sitting where you are tonight. But I believe that the challenges faced
by New York State compel us to find common ground in meeting them.
|