|
Executive Speeches

Testimony of Thomas J. Kelly, Executive Vice
President and General Counsel, New York Power Authority, to the New
York State Assembly Standing Committee on Energy public hearing,
Utica, New York.
August 23, 2006
Good evening, Chairman Tonko and distinguished Members
of the Assembly. My name is Thomas J. Kelly, Executive Vice President
and General Counsel of the New York Power Authority (NYPA).
As you know, the New York Power Authority is the
nation’s largest state-owned electric utility, with 18 generating
facilities in various parts of the state and more than 1,400
circuit-miles of transmission lines. The Authority operates without the
use of tax dollars or state credit, financing its operations with
revenues earned from sales of electricity and through the sale of bonds
and notes for capital projects. The Authority supplies electricity to
government agencies, community-owned electric systems and rural electric
cooperatives, private utilities and to private sector businesses and
non-profit institutions in return for commitments to protect jobs. NYPA
is also a leader in promoting energy-efficiency, new energy technologies
and electric-drive transportation initiatives. Our Mission is to provide
clean, economical and reliable energy consistent with our commitment to
safety, while promoting energy efficiency and innovation for the benefit
of our customers and all New Yorkers.
The topic of today’s hearing, New York Regional
Interconnect, Inc. (NYRI) announced the filing of an Article VII
application to the New York State Public Service Commission (PSC) on May
31, 2006. NYRI is seeking regulatory approval to build a 190-mile high
voltage direct current transmission line from Oneida County to Orange
County. NYRI’s application for the construction of such a power line is
regulated and governed by the PSC under Article VII of the New York
State Public Service Law.
I should note, for the record, that NYPA has no
regulatory powers with regard to the proposed transmission line. Unlike
the Departments of Environmental Conservation, Economic Development,
State, Transportation, Agriculture and Markets, and the Office of Parks,
Recreation and Historic Preservation, NYPA is not a statutory party in
the Article VII process.
Based upon information made available to date, it is
clear that NYRI proposes to interconnect with substations that also
interconnect with NYPA transmission facilities. Consequently, since the
Authority has a direct interest in the impact of any new
interconnections on those substations, we filed on August 9th to
intervene in the Article VII proceedings as an interested party that
will be affected by the proposed project.
On July 26, the PSC issued a deficiency letter and a
procedural ruling in the NYRI proceeding (Case 06-T-0650). Given the
fact that NYRI’s filings, to date, have been determined to be deficient,
we must await more detailed information from NYRI and other parties in
the proceeding before we can, with confidence, offer detailed comment on
the proposal.
To assist the Committee’s deliberations on the matter,
however, we can offer information on the transmission facilities owned
and operated by NYPA.
As I previously mentioned, the Authority owns, operates
and maintains more than 1,400 circuit miles of high voltage (115-kV to
765-kV) transmission lines in New York State. These lines include:
-
a 765-kV line south from the Canadian border to
Marcy, New York;
-
two 345-kV lines from the Niagara Project east to
Niagara Mohawk’s Edic Substation in central New York;
-
two 345-kV lines from Marcy, New York, connecting
to other utility substations in southeastern New York;
-
three 345-kV lines from the Blenheim Gilboa
Project;
-
two 230-kV lines extending east from the St.
Lawrence Project to Plattsburgh, New York, and to the Vermont
border;
-
two 230-kV lines extending south from the St.
Lawrence Project to Belfort, New York;
-
a single circuit, underground and underwater 345-kV
line extending across Long Island Sound between Con Edison’s
substation in Westchester County and LIPA’s substation in Nassau
County, New York; and
-
several 115-kV lines connected directly to large
industrial customers and other shorter lines connecting the
Authority’s generating facilities to the transmission grid.
NYPA has not been engaged in building major new
high-voltage transmission projects since it completed the Long Island
Sound Cable in May 1991. Although it should be noted, for the record,
that we are presently engaged in a transmission reinforcement project
for the Tri-Lakes region of the Adirondacks. Pursuant to an agreement
among the Authority, National Grid, and the Villages of Tupper Lake and
Lake Placid, we have contracted with National Grid for the construction
of substation equipment and a new overhead line to alleviate serious
transmission capacity deficiencies in the Lake Placid, Tupper Lake and
Saranac Lake, New York, area of the Adirondacks. The upgrades will
consist of one 46-kV Static Var Compensator (SVC) at Tupper Lake, with a
projected in-service date of 2006, and one 115-kV SVC at Lake Colby with
a projected in-service date of 2006, and a new overhead 46-kV line from
Stark Reservoir in Parishville to Piercefield with a projected
in-service date of 2008.
Addressing the issue of transmission congestion is not
simply a matter of building new transmission. As the National Electric
Transmission Congestion Study[1],
recently released by the U.S. Department of Energy states: “…congestion
solutions will be based on a thorough review of generation,
transmission, distribution and demand-side options…”
For its part, the New York Power Authority has been
engaged in a range of transmission enhancements, demand-side reduction
and new generation.
The Authority’s major recent focus with regard to
transmission has been the development of new technologies to enhance
existing transmission facilities. We are proud of the pioneering work
done with the Convertible Static Compensator (CSC), installation of
which was completed in the summer of 2004. The CSC is the first device
in the world with the capability of instantaneously shifting power in
the same substation from a heavily loaded transmission line to one with
spare capacity. It is the latest in a series of transmission control
technologies known as FACTS (Flexible Alternating Current Transmission
Systems) that have been developed by EPRI in cooperation with the Power
Authority and several other utilities.
By permitting more electricity to be carried on
existing transmission lines (it can permit total increases of close to
200 megawatts); the CSC serves the reliability and efficiency of the
power system. It has strengthened voltage support on the transmission
system, permitting increased power flows during periods of greatest
electricity use.
The CSC is located at NYPA’s Marcy Substation, right
here in Oneida County, which is the hub of NYPA’s transmission system.
It is adjacent to NYPA’s Frederick R. Clark Energy Center, where the
operations of our generating facilities and transmission lines are
monitored and information exchanged with the New York Independent System
Operator.
NYPA invested $41 million in the CSC, with additional
funding for the $54 million project from EPRI, the electricity
industry's science and technology development organization; Siemens
Transmission and Distribution and more than 30 electric utilities and
independent system operators in the United States, Canada and New
Zealand.
While this individual project serves to address just a
portion of the congestion on the east-west interface, we believe it also
serves as a solid demonstration of the way new technologies can be
developed and applied to enhance transmission.
In addition to innovative transmission technologies,
NYPA has been actively working to reduce demand with energy efficiency
and other demand reduction efforts.
As of June 30, 2006, the Authority has invested $984
million in energy-efficiency upgrades for 2,388 elementary and secondary
schools, colleges and universities and government buildings across the
state. In total, these energy-saving projects have reduced demand by 198
MW statewide, with 62% of the load-reduction taking place in the heavily
congested New York City/Long Island region.
In addition to these energy-efficiency savings, NYPA
operates a Peak Load Reduction Program that enlists our largest New York
City customers to cut demand on peak load days. In total, the
contributions of NYPA and its customers to New York State’s Combined
Demand Reduction Initiative totals more than 333 MW of reduced load.
While transmission innovation and demand reduction can
play valuable roles, the development of a robust, reliable marketplace
for electricity in New York State will require continued development of
new generation. Market economics suggest that new generation should be
built close to the load, the areas with the greatest demand for
electricity.
Over the past dozen years, NYPA has been working to
increase the generating capacity of the downstate region, adding more
than 1,000 MW in generation on Long Island and in New York City.
NYPA’s Flynn Power Plant in Holtville, Suffolk County,
is a 135 MW combined-cycle electric plant which began commercial
operation in May 1994. Annually this plant produces about 1.1 million
megawatt-hours (MWh) of electricity and since its inception has produced
over 11 million MWh of electricity.
The PowerNow! Program increased NYPA’s generating
capacity in the metropolitan New York City region by about 450 MW during
summer 2001. These small, clean power plants were all installed
downstate -- at two sites in the Bronx, two in Brooklyn, one in Queens,
one on Staten Island and one in Brentwood, in the Town of Islip, Long
Island.
NYPA launched that program in late August 2000 to
install these small, clean power plants in response to warnings from
officials in the public and private sectors that the New York City
metropolitan area could face power shortages in the summer of 2001.
The small plants proved invaluable during an August
2001 heat wave, when temperatures—and electricity use—soared to new
highs, and in the summer of 2002, when Con Edison and the Long Island
Power Authority each set records for three-month electricity use. The
units again proved their worth in the wake of the September 11 terrorist
attacks; when they were called on to generate power because their
diverse locations were a security asset. During the northeast blackout
of August 2003, the plant's helped return power to New York City while
stabilizing the downstate transmission system.
NYPA’s newest power plant, the 500 MW Combined Cycle
Power Project in Astoria, Queens began commercial operation in December
2005. The location for the new plant is a seven-acre parcel that is part
of a 47-acre site the Power Authority owns in Astoria, Queens. The new
facility is adjacent to the Poletti project, an 885-megawatt generating
facility that also runs on natural gas, with low sulfur oil as a backup
fuel. As a condition of the permit for the new plant, the Poletti
project is scheduled to be retired no later than 2010.
Building generation where it is most needed is the most
appropriate approach to addressing the Empire State’s electric power
concerns.
Toward that end, it is essential that New York State
re-establish a regulatory structure that effectively administers the
power plant siting process. Unfortunately, New York’s Article X power
plant siting law expired in 2002 and agreement to extend the law has yet
to be reached.
New York needs new power plants to be built and our
citizens need a law that protects environment and preserves the public
interest in siting process. We certainly encourage the Assembly to
continue to work to achieve this essential step on the path to a secure
energy future for the Empire State.
Thank you for the opportunity to testify. I will do my
best to answer any questions you may have.
National Electric Transmission
Congestion Study, Executive Summary,
U.S. Department of Energy, August 8, 2006.
|