|
Executive Speeches

Remarks of Louis P. Ciminelli, chairman of the New York Power
Authority, to the Conference Board of Canada, Toronto, Ontario,
Canada.
January 29, 2004
Good afternoon. It’s a pleasure to be here for this
most timely and important conference.
I think it’s fair to say that ever since the Treaty of
Ghent ended the War of 1812, our two countries—despite inevitable
disagreements at times—have tended to look toward each other in
friendship and mutual understanding. And nowhere is this more evident
than in the realm of electricity.
I’m particularly pleased that my organization—the New
York Power Authority—has had a marvelous working relationship with
Canadian utilities for just about half a century. In fact, our first
generating facility, on the St. Lawrence River, was a joint
Canadian-American effort—and a truly exceptional one.
This vast hydroelectric project spans the international
border and has 16 generating units on each side. It was completed
virtually on the basis of a handshake between Robert Moses, the Power
Authority’s chairman, and Robert Saunders, his counterpart at Ontario
Hydro and a former mayor of Toronto. The costs and the work were
shared—without formal written agreements.
The first electricity flowed in 1958, just four years
after construction began—and the project was fully operational in
five. That met the ambitious targets Moses and Saunders had set—and beat
the requirement in the Power Authority’s federal license. When the work
was finished, Chairman Moses said, “We have learned an ancient
truth—that men of good will working together are unbeatable.”
That was demonstrated, too, through the construction by
our two federal governments of the St. Lawrence Seaway in conjunction
with the power project. Another extraordinary achievement—and one, by
the way, that wouldn’t have been possible without the power development.
Even before any of this happened, Canada and the U.S.
had signed a treaty in 1950 permitting increased diversion of water from
Niagara Falls for power production while at the same time maintaining
the beauty of the Falls. The treaty called for the additional water to
be shared equally between our two countries.
At first, Ontario Hydro was able to use some of the
U.S. water because it forged ahead and built new hydro generation while
a lengthy debate raged over public vs. private development on our side.
Eventually, though, the Power Authority was tapped to build the
2,400-megawatt Niagara Project—which began operation in 1961 as what was
then the largest hydroelectric facility in the Western World. And, as
envisioned by the treaty, we’ve been sharing the water ever since.
Our ongoing cooperative relationship with Canadian
entities takes several other forms. These range from our daily work with
Ontario Power Generation on matters concerning the hydroelectric
projects on both sides of the border to our involvement in the
activities of the International Joint Commission and its affiliated
agencies with respect to water flows and related issues. Then, there are
the more visible connections in the form of the 765-kilovolt
transmission line that the Power Authority built from Quebec to Central
New York in the 1970s and the five 345-kv and 230-kv transmission links
between our hydro projects and Ontario.
Of course, the electrical ties between our countries
span the continent. It’s no wonder, then, that the U.S.-Canada trade
relationship—the strongest in the world—has a significant electricity
component. This suggests a high degree of integration between the
wholesale electricity markets—and the power grids themselves—in our two
countries.
Just how extensive that integration has become was
vividly demonstrated late in the afternoon of last August 14. Before
that day’s blackout struck, Ontario had been importing a large—but not
unusual—amount of electricity from the United States. As the interim
report of the U.S.-Canada Task Force on the blackout made clear, the
power flows to Ontario were within acceptable operating limits and were
not a cause of the ensuing debacle.
Without question, the problems began elsewhere—south of
the border, in Ohio.
The story, by now, is familiar: As transmission lines
and power plants in the U.S. Midwest went down in a cascading failure,
there was a huge rush of power from the Mid-Atlantic states, around Lake
Erie and through New York and Ontario to serve loads in Michigan and
Ohio. The resulting strain on the interconnected system ultimately left
about 50 million people here in Ontario and in eight states without
electricity.
In New York State, the Power Authority’s St. Lawrence
and Niagara hydroelectric projects were the only major power plants to
keep operating throughout the blackout. Meanwhile, Ontario Power
Generation’s Beck and Saunders hydro stations also stayed on line and
remained connected to New York, along with some Ontario load. The four
large hydro projects, together with our 765-kv line from Quebec and
several other transmission facilities in New York, ended up as an
electrical island of about 5,700 megawatts of demand that escaped the
blackout. And—as the interim report noted—this island formed the basis
for restoration of the systems in Ontario and New York.
Our success in keeping the lights on in even a
relatively limited area during the cascade was due to a combination of
luck and physics. But in the period that immediately followed, it
reflected the skilled coordination of power plants and transmission
lines by operators on both sides of the border and the steadfast
matching of generation and load to keep the electrical island in service
and to help restore the areas that were blacked out. And it showed the
value of the physical connections—and of the longstanding cooperative
relationship—between New York and Ontario.
In the blackout’s aftermath, we’ve also heard a good
deal about the disadvantages of our electrical interdependence. As the
events of August 14 showed, problems and deficiencies in one country can
quickly spread across the border. With this in mind, there have been
calls in Canada for increased emphasis on an east-west domestic grid as
opposed to the north-south ties to the United States.
Such concerns are understandable. But we must not
retreat into a form of protectionism in electricity trade that would run
counter to both our history and our best interests. And we must not
permit the blackout to provide a rationale for reversing efforts on both
sides of the border to create competitive, restructured electricity
markets.
It’s undeniably true that competition and deregulation
have put increased strains on a power system that was not designed to
carry large amounts of electricity over long distances. However, the
blackout was due not to deregulation—but to a combination of human
error, computer and communication problems and, most important, the
absence of mandatory and enforceable reliability standards.
Our response must be to acknowledge that deregulation
and the greater flow of electricity between different areas have, in
fact, created new reliability challenges—and that these challenges
should have been anticipated. We must then move to address them by
putting mandatory, enforceable standards in place on an international
basis and assuring that those standards are met.
This is an imposing task. But it is a task that we
must aggressively undertake—and one for which we are already well
positioned.
Since 1968, we have worked together through the North
American Electric Reliability Council, or NERC—and its 10 regional
councils—to promote a secure and dependable power supply. NERC was
established in response to the major blackout that hit the Northeastern
United States and Canada in 1965. Its creation was a significant
achievement. For the first time, we would join to plan and control the
flow of electricity both within and across our borders.
NERC and the regional councils establish standards for
performance in such areas as operations, maintenance, planning and
general policy. But the problem—as I indicated a moment ago—is that
these standards are voluntary. And the only sanctions for violating them
are so-called simulated monetary penalties.
That’s not good enough. In 2002 alone, there were 444
violations of NERC’s voluntary standards. And the interim Task Force
report cited a total of six that contributed directly to last August’s
blackout.
The Northeast Power Coordinating Council—the regional
group that covers New York and the New England states, as well as
Ontario, Quebec and the Maritime Provinces—has established standards
that go beyond NERC’s and are the strictest of any regional council’s.
These standards are mandatory—and violations result in potentially
embarrassing letters.
In New York, our State Reliability Council has set
mandatory rules that in some cases are more stringent than even the
NPCC’s. Market participants must meet the standards under tariffs that
have been approved by FERC—the U.S. Federal Energy Regulatory
Commission. Again, there are no monetary penalties, but peer pressure
has been effective.
I’m less concerned about the specific nature of the
penalties than about the compelling need for mandatory standards.
The energy bill that has thus far failed to pass the
U.S. Senate would take a big step in that direction by authorizing the
federal commission to designate an organization—which could well be
NERC—to establish and enforce national standards.
With the legislation tied up, FERC Chairman Pat Wood
initially said the Commission planned to act on its own and to put
mandatory standards in place by this summer. Now, however, FERC is
working with utility officials to try to develop a mutually-acceptable
approach. And the Chairman has stated that the best solution would be
to clearly resolve the issue by passing the energy bill.
Once the situation is settled in the U.S., it should be
feasible to devise a single set of standards that are truly
international in scope.
Besides pushing for mandatory reliability standards in
the United States, FERC wants to require—or, at the very least, strongly
encourage—utilities to relinquish operational control of their
transmission systems to regional or statewide organizations. The thought
is that this will improve regional coordination of generation and
transmission and lead to increased system reliability and lower prices.
It didn’t help matters during the blackout that the
Midwest Independent System Operator is essentially just a monitor and
doesn’t have operational authority. In fact, there are 37 separate
control areas within the Midwest ISO’s territory—and about 140
throughout North America. In contrast, entities such as the New York
Independent System Operator, ISO-New England, the Ontario Independent
Electricity Market Operator and Trans-Energie in Quebec have full
operational control over their areas. Establishing similar clearcut
responsibilities for a limited number of organizations in the U.S.
should strengthen system reliability and facilitate coordination with
Canadian systems.
Nevertheless, the FERC vision of compulsory Regional
Transmission Organization or Independent System Operator membership has
sparked intense opposition in some parts of the U.S. and would
effectively be rejected under the energy bill if the legislation gets
through Congress.
Even with the bill in limbo, Chairman Wood has
apparently recognized the political realities and said the Commission is
prepared to offer incentives that would make a voluntary approach “very
attractive.” He also maintains that FERC has the legal authority to go
the compulsory route if it chooses to do so. So things could get
interesting.
Regardless of what happens with RTOs—or reliability
standards—it’s clear that the appropriate entities in our two countries
need to work together to develop a coordinated planning process that
will minimize the likelihood of future blackouts or less serious
disruptions. This is imperative. But—surprisingly enough—calls for major
investment in new transmission lines may be wide of the mark in at least
some instances.
Contrary to what we often hear, simply building new
transmission will not necessarily make the system more reliable. Indeed,
it might make it less so. This is sort of our version of chaos theory.
Increase the number of interconnections, and the risk of widespread
catastrophic failure rises as problems spread more easily between
systems.
The fact is, reliability isn’t just a result of how
much transmission we’re able to put up. Indeed, it can often be achieved
more effectively—and more economically—by building power plants closer
to load centers, installing distributed generation or promoting energy
efficiency.
System planners must choose the best solution—or
combination of solutions—to reliability problems without foreclosing any
options. Ideally, the markets should provide the right answer, but the
electric utility industry is not yet a fully competitive marketplace.
As we head toward that goal, there may well be cases in
which new transmission—whether or not needed to maintain reliable
service—can reduce congestion and potentially carry lower-cost power to
high-priced areas. In New York State, at least two—and possibly
three—proposed lines would bring electricity from Canadian and upstate
sources to the New York City area. One of them, a 500-kilovolt
direct-current facility, is planned by a Toronto developer—Pegasus Power
Systems. Of course, only time will tell whether the proposed lines will
be licensed by the regulatory authorities and—if so—whether they’ll
lower overall costs for consumers.
The increased attention to DC lines is particularly
noteworthy in the wake of the blackout since—unlike AC
facilities—they’re normally not affected by disturbances elsewhere on
the interconnected system. Indeed, the U.S.-Canada Task Force report
stated that Quebec was largely spared from the blackout’s effects
because it’s linked to neighboring systems almost entirely with DC ties.
When we think about investment in the grid, though, we
should focus not only on new lines, but also on new technologies that
can give us a smarter, stronger, more fail-safe system.
In particular, the blackout showed that we need
improved visualization and signaling within and between regions.
With a better picture of grid conditions—and new
digital devices to help control power flows, voltages and
surges—operators could respond to and possibly avoid problems that might
trigger blackouts or other system disturbances.
I’m pleased to tell you that the Power Authority has
essentially completed installation of such a device—the most advanced in
the world. This “convertible static compensator” will for the first time
demonstrate the capability to simultaneously control flows on two
high-voltage lines and thus to potentially transfer power from
heavily-loaded circuits to those with spare capacity.
While we’ve paid the bulk of the project cost of 54
million U.S. dollars, about 30 other utilities and power industry
organizations—including BC Hydro and what was Ontario Hydro—have
provided financial support. We think this is a sign that others
recognize the technology’s future benefits to power systems in our
countries and beyond.
Promising though they are, new technologies will bring
maximum benefit to Canada and the United States only if we work together
in their development and implementation. That’s even more true when it
comes to reliability standards and coordination of planning and
operations for a North American grid that functions without regard to
international borders.
Fortunately, as I noted at the start, this spirit of
cooperation is very much in keeping with the history and traditions of
our two countries. I’m reminded of this every time I visit the great
hydro project on the St. Lawrence.
A monument at the center of the Moses-Saunders Power
Dam—unveiled by Queen Elizabeth at the project’s dedication 45 years ago
this coming June—carries the inscription: “This stone bears witness to
the common purpose of two nations whose frontiers are the frontiers of
friendship, whose ways are the ways of freedom, and whose works are the
works of peace.”
These words celebrate a magnificent accomplishment in
which an international border was transcended not only by a massive
power dam, but by the dreams and aspirations of people on either side.
As, together, we face the challenges and opportunities of a vastly
different power industry, these same words can provide guidance and
inspiration. I hope—and trust—that we will take them to heart.
Thank you very much. |