|
Executive Speeches

Remarks of Eugene W. Zeltmann, president & chief
executive officer of the New York Power Authority, at the Municipal
Analysts Group of New York, New York City, New York.
October 15, 2003
A few years ago, “USA Today” asked its readers: “What
is the greatest invention of all time?” Overwhelmingly, they answered,
“electricity”—probably because of all the inventions that electricity
makes possible.
More recently—in a somewhat similar vein—the National
Academy of Engineering asked its members: “What is the greatest
technological advance of the past 100 years?” The answer: “North
America's power grid”—the finely-wrought system that delivers the
greatest invention of all time.
The polls have spoken. But the blackout this past
August proved that even in America, the grid can suffer gridlock—and far
worse. The reason is clear once you realize that electricity is among
the few commodities that is produced and consumed in the same instant.
That alone makes it very challenging to deliver—especially over long
distances.
The North American grid that carries electrons to our
computers and TV sets is, in essence, one huge electrical circuit. And
if that circuit breaks at any point, the system must instantaneously
reroute power—or other lines and power plants will fall like so many
dominoes, causing massive blackouts.
The amazing balancing act performed every day by those
who manage the grid is veiled by their success. We take it for granted
until things fall out of balance as they did on August 14.
The next-to-last big American blackout occurred almost
exactly seven years before this most recent one. Back in August of
1996, the lights went out along the Pacific Coast from Oregon to San
Diego and into Mexico, with the outage doglegging east as far as Texas.
Power lines that failed in the Northwest affected four main arteries
that sent the power south.
The reasons for the recent failure—and why some areas
of the Northeast managed to escape it—are still unclear as various
investigations continue.
But whatever the cause, the Blackout of 2003 was a
defining moment for everyone in the electric power business. A moment
like those in 1996—and in 1965 and 1977, when major blackouts hit this
part of the country.
There were many who told us—before Thursday, August
14—that this couldn’t happen again. Some who warned that it might
happen again. And none with quick or easy answers when it did happen
again.
I spent all that Thursday night, and the next day, in
the Power Authority’s Albany office—receiving and analyzing reports on
the painstaking process of restoring over the course of many hours a
power system that had shut down in minutes—even seconds—in the wake of
what apparently began as relatively localized problems in the Midwest.
Fortunately, the Power Authority’s Niagara and St.
Lawrence-FDR hydroelectric projects stayed on line when the blackout
struck—and were the only major power plants in New York State to keep
operating.
In the early stages, Niagara and St. Lawrence were
supplying about 60 percent of the electricity still flowing in the
state—with much of the rest coming from Quebec on the Authority’s
765-kilovolt transmission line and from generation in Eastern Ontario.
Later, the two hydro projects—along with our Blenheim-Gilboa
pumped storage project in Schoharie County—were the main electrical
building blocks that enabled the statewide system to return to service.
In addition, a series of small, clean power plants that
we installed in New York City in 2001—and our Poletti project in
Queens—played key roles in bringing the lights back on in the city.
Four of the 10 small units were on line Thursday night and the
others—along with Poletti—began operating at various times on Friday
morning.
I should also note that the Central Park police station
in Manhattan was completely unaffected because all its electricity comes
from a 200-kilowatt Power Authority fuel cell on the site.
The Economist magazine observed, ironically, that
thanks to the fuel cell, Central Park might have been the safest place
to be in New York City during the blackout.
Although our projects—large and small—performed well,
we did have to deal with seriously erroneous reports that attributed the
blackout to a lightning strike at Niagara. Here we had this project
doing yeoman service—with no lightning within hundreds of miles—and it
was being singled out by public officials and the news media as the
source of the problem.
Now, as I mentioned before, the task of determining
what actually happened—and why—is well under way. We must learn all we
can from what went so terribly wrong. And we must use those lessons to
take quick and effective corrective action.
A reliable power supply doesn’t happen by accident.
Indeed, it requires effective and concerted action in three
areas—building clean new power plants, strengthening the transmission
system and carrying out aggressive energy-efficiency measures. Each of
these areas is vital—and, ideally, efforts in each will complement the
others.
Not surprisingly, though, much of the attention in
Congress and elsewhere these days is focused on ways to strengthen the
transmission system. That’s a welcome development, because with the
coming of competition to the power industry—and the need to send more
power over longer distances—we’re placing unprecedented demands on a
grid that wasn’t designed to meet them.
Clearly, we must provide the investment incentives,
the cost-recovery mechanisms and the efficient regional planning
processes that will enable us to build new transmission when and where
it’s required.
In addition, the blackout has underscored the need for
a consistent set of mandatory national reliability standards for our
industry.
In response to the blackout of 1965, the North American
Electric Reliability Council—or NERC—was created to set standards and
rules for planning and operating the bulk power system. But the rules
are voluntary and are not always observed.
The absence of mandatory standards has produced a
balkanized expanse of hundreds of power plants and thousands of miles of
transmission lines, divided up into scores of different control areas,
each run by different authorities.
You might be dismayed—as I
was—to learn that electricity in the Balkans is far less balkanized than
in the U.S.
The sixth largest power dam
in the world—the first ever built on the Danube—serves the electricity
needs of Yugoslavia, Bosnia and Herzegovina and parts of Bulgaria in a
unified grid. And since Italy had its own blackout just a little over
two weeks ago, I’m sure there were plenty of Italians looking across the
Adriatic in wonder that the lights were still on in the Balkans.
I’m pleased to report that New York not only has met
NERC’s voluntary standards, but has gone beyond them with some of the
strictest state electric system reliability rules in the nation.
But, with power transactions between states and regions
continuing to increase, I think it’s essential for Congress—in this
session—to pass an energy bill that includes mandatory national
reliability standards. And the legislation should enable individual
states—such as New York—to impose still stricter rules as long as doing
so doesn’t adversely affect other parts of the interconnected grid.
That would be a major step forward—but it would still
leave us with the problem of inadequate investment in the transmission
system.
In a report issued shortly after the recent blackout,
EPRI, the power industry’s research arm, warned that investment in
infrastructure—as a percentage of company revenues—had sharply declined
over the years. Almost incredibly, it found that the figure in the ’90s
was less than half the historic minimum lows during the Depression.
As EPRI’s vice chairman, I can tell you that the report
had been in the works for about a year and was actually completed just
over a week before the blackout. But what happened on August 14 did
nothing to weaken its case for a dramatic increase in expenditures on
the grid.
Now—more than ever—we must encourage investment in
transmission by utilities, merchant companies and others in the private
sector. And the way to do this is to cut through the morass of
conflicting state and federal regulations and develop clear rules and
cost-recovery mechanisms for transmission owners and other potential
investors. This, in turn, will encourage them to finance upgrades to
the grid when they’re needed for reliability or market efficiency
purposes.
Governor Pataki said it well in testimony submitted to
a Congressional committee shortly after the blackout: “Without clear
incentive, there will be no investment. Without investment, we cannot
guarantee it will not happen again.”
As things now stand, there are simply too many
uncertainties for investors. And—because the power system transcends
state borders—it will for the most part be up to the federal government,
through Congress, to resolve them.
In a related matter, we face
the continuing need to allocate transmission costs as fairly as possible
at the retail level.
Keep in mind that there are
two ways of recovering costs from retail customers. One is the
traditional “socialized” approach of having all customers in a given
system share the costs as part of the regulated rates. The
other—so-called “participant funding”—is to pass the costs on to only
those customers that directly benefit from a new facility.
Our thinking at the Power
Authority is that socialized costs would be appropriate if an
independent system operator or regional transmission organization—having
the proper authorization—directed a utility or transmission owner to
build new transmission for reliability purposes.
But if a company, on its
own, made a business decision to build a line to ease congestion in a
particular area, chances are it would be competing against existing or
proposed power plants. In that case, the company should be responsible
for recovering costs through the sale of transmission capacity to
load-serving entities—or to those power producers that stand to benefit
from the project.
The issue of market-based
incentives for merchant companies is particularly difficult because
there’s a real risk that a new generating plant could impact a
transmission project’s value by reducing or eliminating congestion.
As we seek to bolster the system, we must also
recognize that the success of competitive wholesale electricity markets
depends at least in part on the capability of the transmission
interconnections between multi-state regional transmission organizations
or independent system operators.
The establishment or strengthening of such
organizations is a cornerstone of the Federal Energy Regulatory
Commission’s vision for the electric power industry. And they will, in
fact, have to take a large part in transmission planning and siting,
especially since new facilities may well extend over long distances and
multiple jurisdictions.
Here in New York, the ISO is
working to establish comprehensive planning processes—both within the
state and as part of a coordinated regional effort.
Progress in strengthening the state’s transmission
system has been slow. But there was recently an encouraging development
when the state Senate passed legislation that Governor Pataki had
proposed to facilitate upgrading of transmission lines in New York and
provide financing for transmission and generating facilities through the
state Energy Research and Development Authority. The proposal would
establish some sensible streamlining for transmission upgrades along
existing rights-of-way, so I hope the Assembly will give it serious
consideration.
As you may have heard, one new project—an underwater
cable from Connecticut to Long Island—was completed last year, but was
prevented from operating because of environmental concerns in
Connecticut.
In response to a request from Governor Pataki and other
New York officials, the Secretary of Energy has authorized emergency use
of the cable—which can carry 330 megawatts of electricity—at least until
issues concerning the blackout have been resolved. But we may not have
heard the last word since Connecticut has been granted a rehearing of
the Secretary’s order and is also pursuing a separate court action.
No matter how this eventually plays out, the Sound
Cable Saga will stand as a textbook case of how tough it is to site,
build and operate a new transmission line.
Nevertheless, there has been some news lately
concerning two potential projects.
The developers of the Empire Connection—a largely
underground facility that would carry 2,000 megawatts from the Albany
area to New York City—announced last month they had secured an initial
commitment for $200 million in equity funding for the $700 million
project. That’s a major accomplishment in this day and age when
financial backing for transmission—or generation—projects is so
difficult to obtain.
Then—last week—a Toronto developer said it hopes to
build a 500-kilovolt line from the Utica area, southwest to Binghamton
and on to Northern New Jersey and New York City. The line would carry
between 2,400 and 3,000 megawatts from upstate and Canadian sources.
I should mention that these two projects—like the cable
from Connecticut and a couple of proposed lines that would carry power
from New Jersey to New York City and Long Island—would be direct-current
facilities. Flows on all of them would be easier to control than on
conventional AC lines and less vulnerable to convulsions on other parts
of the grid—such as those that occurred in August.
Those problems arose even though the grid was not
particularly stressed at the time of the blackout as power plants were
generating below their peak loads.
This fact has focused attention on an intriguing
possible cause of the blackout—a phenomenon known as “reactive power.”
Reactive power—which is essential to maintaining system
stability—can be produced by generating plants or by other types of
electrical equipment. But there is less financial incentive to produce
it in today's deregulated markets because generators get paid more money
to produce megawatts that can be sold to wholesale customers.
Maintaining a sufficient reactive power supply is a
constant worry for electric-system operators. If voltage levels begin
to deteriorate through the loss of power lines, for instance, it becomes
more difficult to provide the reactive power needed to keep the system
stable.
This strengthens arguments for a dramatic increase in
expenditures to create a “smarter grid.”
Indeed, the EPRI report I mentioned earlier called for
unleashing “the innovative technology” needed to create a power delivery
network based on real-time digital controls rather than today’s
relatively slow electromechanical switches.
Digital switch controls could route power over
different lines and help to control power surges that might otherwise
trigger blackouts. Sensors and dedicated communications links would
feed information about the state of the grid to energy control centers
that would oversee the switches.
The Power Authority has installed a device at our Marcy
Substation near Utica that achieves this kind of control. It’s called a
convertible static compensator—or CSC—and like an efficient railroad
signalman, it can help both in avoiding disasters and in improving the
efficiency of the transmission system.
When the CSC is fully operational later this year, it
will be the world’s most advanced device for controlling
transmission-line voltage and power flows—and will permit operators, for
the first time anywhere, to instantly move power from a heavily-loaded
line to one with spare capacity.
Conceivably—with enough of these devices installed at
strategic points on the grid—we could significantly reduce the need for
new transmission lines. Just our single device at Marcy has boosted
statewide transmission capacity by nearly 200 megawatts.
The Power Authority has invested $41 million in the CSC—and
the remainder of the total cost of $54 million has come from about 30
electric utilities in the U.S. and abroad and several industry
organizations.
We know it could be a long time before we recover our
share through transmission revenues—and that there are no guarantees we
ever will. Nevertheless—as a public entity—we thought it was important
for us to be out front in demonstrating this technological
breakthrough. Now the challenge is to convince transmission owners and
others in the private sector to adapt this and other innovations to
their own needs.
It’s hard to find anything positive in the events of
August 14. But if the blackout helps pave the way to the creation of a
truly sophisticated power system—operating at maximum efficiency—it will
have served a tremendously beneficial purpose. And if we act now, I’m
confident that in the future, the members of the National Academy of
Engineering—and all who depend on electricity—will have even more
compelling reasons to view the North American grid as a technological
marvel. |