|
Just in Time for Summer's High Demand for
Electricity, NYPA Completes Third Unit Upgrade at Blenheim-Gilboa
Project
Contact:
Steve Ramsey
1-800-724-0309
steve.ramsey@nypa.gov
June 17, 2009
FOR IMMEDIATE RELEASE
NORTH BLENHEIM—New York Power Authority (NYPA)
President and Chief Executive Officer Richard M. Kessel today
announced that the Blenheim-Gilboa Pumped Storage Power Project is
ready for the peak-demand summer season, following the completion of
work on the third of four pump-turbine generating units as part of a
multiyear Life Extension and Modernization (LEM) program at the
hydroelectric project.
“Thanks to the extraordinary efforts of the
Blenheim-Gilboa LEM Project Team, this exceedingly difficult and
complex project was completed safely, successfully, on budget and in
time for the peak-use season for electricity,” Kessel said. “When
we turn on our fans and air-conditioners this summer we should
remember the dedication and hard work at Blenheim-Gilboa over the
winter months, so New York gets the energy it needs, when it’s
needed most.
“Keeping the fast-track pace we set for the upgrade
project is one way the Power Authority is intensifying its efforts
to help achieve Governor Paterson’s ‘45 by 15’ goal to meet 45
percent of the state’s electricity needs through improved energy
efficiency and clean renewable sources, like the power produced at
Blenheim-Gilboa, by 2015.”
The newly refurbished generating unit resumed
commercial operation on May 30, after being out of service since
Sept. 15, 2008. Despite the challenges of some delayed equipment
deliveries, including a head cover and a lower ring, NYPA workers
were able to complete the upgrade on schedule.
“It takes a year or more to manufacture some of
the turbine parts,” said Lynn Hait, regional manager of Central New
York, NYPA. “We order them ahead of time and, when necessary, adapt
the upgrade work to any changes in deliveries because there is no
room at this facility to store the large components. For example,
the generator's main rotor, which weighs 500 tons, is as big as a
house, and cannot be stored outdoors.”
The Blenheim-Gilboa project moves water between
lower and upper reservoirs. At night, when the need for energy is
low, the project’s dual-function pump turbine-generators move water
from the lower reservoir to the upper reservoir on Brown Mountain.
In the morning, when consumer demand for energy is increased, the
water is released from the upper reservoir and plunges 1,200 feet to
power the pump turbine-generators. The water then flows into a lower
reservoir on Schoharie Creek.
When the project’s third pump-turbine generator was being
refurbished the other pump-turbine generators were operating, except
for a seven-week period when it was necessary to shut down the 1,040
megawatt (mw) project. During that time the water level in the
facility’s upper reservoir was considerably reduced in order to
accomplish the replacement of a spherical valve on the unit being
refurbished. The valve controls the flow of water into the
pump-turbine generator.
In September, the Power Authority will begin work
on the fourth pump-turbine generator, which is the final unit to be
upgraded. The unit is slated to be returned to service in June 2010
and will mark completion of the LEM program. The newly designed
turbines, together with other new and refurbished components, allow
each of the massive generators to realize improved efficiency which
is estimated to increase its maximum capacity from 260 mw to
approximately 290 mw. At the conclusion of the LEM program, it is
projected the Blenheim-Gilboa project will be capable of producing
approximately 1,160 mw of electricity.
The LEM program marks the first time the
pumped-storage project has been refurbished since it went into
service in 1973. The $135 million upgrade will allow Blenheim-Gilboa
to produce more power from the same amount of water while extending
the facility’s record of reliable service for decades ahead.
NYPA is currently conducting a LEM program at its
St. Lawrence-Franklin D. Roosevelt Project in Massena, with that
initiative expected to be completed by 2013. It also completed a
15-year upgrade of its Niagara Power Project, near Niagara Falls, in
late 2006 to enhance the efficiency of the project’s main generating
facility and extend its operating life.
About NYPA:
■ NYPA uses no tax money or
state credit. It finances its operations through the sale of
bonds and revenues earned in large part through sales of
electricity. ■ NYPA is a leader in promoting
energy-efficiency, new energy technologies and electric
transportation initiatives. ■ It is the
nation’s largest state-owned electric utility, with 18 generating
facilities in various parts of the state and more than 1,400
circuit-miles of transmission lines. For more
information,
www.nypa.gov.
Return to Press Center
|