|
Power Authority Completes
Upgrades on Generating Unit at Its Blenheim-Gilboa Project in Time
for Peak-Demand Season
Contact:
Steve Ramsey
1-800-724-0309
steve.ramsey@nypa.gov
June 3, 2008
FOR IMMEDIATE RELEASE
NORTH BLENHEIM—The New York Power Authority’s
(NYPA) Blenheim-Gilboa Pumped Storage Power Project is ready for the
peak-demand summer season, following the completion of work on the
second of four pump-turbine generating units as part of a multiyear
Life Extension and Modernization (LEM) program at the hydroelectric
project.
The current LEM program marks the first time the
project has been refurbished since it went into service in 1973. The
$135 million upgrade will allow Blenheim-Gilboa to produce more
power from the same amount of water while extending the facility’s
record of reliable service for decades ahead.
“The extraordinary effort of those working on the
Blenheim-Gilboa upgrade is clearly shown by their prompt completion
of the latest phase of the LEM in time for the peak-demand summer
season,” said Roger B. Kelley, NYPA president and chief executive
officer. “The installation of the four new pump-turbines and
modifications to other equipment will ensure that this project
operates at the highest efficiency, furthering the vital role that
the facility plays for reliable, clean and economical electricity
for New York State.”
The newly refurbished generating unit resumed
operation on June 1 after being out of service since mid-September
2007. Despite the challenges of some delayed equipment deliveries,
NYPA workers were able to complete the upgrade on schedule.
The three other pump-turbine generators at the
Blenheim-Gilboa project operated most of that time, except for a
seven-week period when it was necessary to shut down the
1,040,000-kilowatt project to facilitate the work. During that time
the water level in the facility’s upper reservoir was reduced in
order to accomplish the replacement of a spherical valve on the
refurbished unit. The valve controls the flow of water into the
project powerhouse.
In September, the Power Authority will commence
work on a third pump-turbine generator, with that unit slated to be
returned to service in June 2009 following a schedule used for the
first two units. The work on the final pump generating unit will be
undertaken in the same manner the following year, with the LEM
program scheduled for completion in June 2010.
The Blenheim-Gilboa project moves water between its
lower and upper reservoirs, for a pumping-generating cycle that
provides economical power during times of peak demand. At night and
on weekends, when demand is lower, water is pumped to the upper
reservoir, atop Brown Mountain, using the least cost electricity
available from other sources. During periods of greatest consumer
demand, water is released from the upper reservoir, plunging 1,200
feet to power the dual-function, pump turbine-generators and then
flows into a lower reservoir on Schoharie Creek.
NYPA is currently conducting a LEM program at its
St. Lawrence-Franklin D. Roosevelt Project in Massena, with that
initiative expected to be completed by 2013. It also completed a
15-year upgrade of its Niagara Power Project, near Niagara Falls, in
late 2006 to enhance the efficiency of the project’s main generating
facility and extend its operating life.
The Power Authority’s hydroelectric facilities
account for about 75 percent of the statewide public power utility's
total generating output.
About NYPA:
■ NYPA uses no tax money or state
credit. It finances its operations through the sale of bonds and
revenues earned in large part through sales of electricity. ■
NYPA is a leader in promoting energy efficiency, new energy
technologies and electric transportation initiatives. ■ It is
the nation’s largest state-owned electric utility, with 18
generating facilities in various parts of the state and more than
1,400 circuit-miles of transmission lines. ■ For more
information, please go to www.nypa.gov.
Return to Press Center
|