|
NYPA Marking 50th
Anniversary of Niagara Construction Start:
Program Planned for Power Vista
Contact:
Lou Paonessa
716-286-6651
louis.paonessa@nypa.gov
March 24, 2008
FOR IMMEDIATE RELEASE
LEWISTON—The New York Power Authority (NYPA) will
mark the 50th anniversary of the start of construction of the
Niagara Power Project with a special program at the Power Vista, the
project’s admission-free visitors center, on Saturday, March 29.
Ken Glennon, an author who worked on project
construction for Merritt-Chapman & Scott, a principal contractor,
will recall his experiences in presentations at 11 a.m. and 1 p.m.
in the center’s Community Room. The program will be part of the
Power Vista’s yearlong series of “Sensational Saturdays” events.
“The Niagara project was the largest hydroelectric
development in the Western World when it was built and it stands
today as the biggest electricity producer in New York State,” Roger
B. Kelley, NYPA’s president and chief executive officer, said. “This
is a fitting time to pay tribute to the men and women who built this
magnificent source of clean, renewable and economical energy.”
Construction of the project began in earnest in
March 1958. The extraordinary effort, which involved as many as
11,700 workers, led to the start of power production within three
years, in January 1961, and to completion of the project by October
1962.
The 2,441-megawatt Niagara project today produces
some of the nation’s least-expensive electricity, with allocations
to businesses in Western New York helping to protect about 45,000
jobs. The project, which itself employs more than 300 workers, also
supplies low- cost power to New York State’s 51 municipal
electric systems and rural cooperatives and to three upstate
utilities—National Grid, New York State Electric & Gas and Rochester
Gas and Electric—for resale to their residential
consumers without profit.
On March 15, 2007, the Power Authority received a
new 50-year federal operating license for the project, more than
five months before the original license expired. Issuance of the new
license followed an innovative process in which local communities,
environmental groups and other interested parties participated from
the outset.
Under a series of agreements resulting from the
cooperative procedure, the Power Authority is providing various
economic, environmental and recreational benefits on the Niagara
Frontier, including: low-cost power allocations and payments to
communities in the project area, the Tuscarora Nation and Niagara
University; funding for improvements to the Buffalo waterfront;
implementation of habitat improvement projects in the Niagara River
Basin; and enhancements to facilities operated by the state Office
of Parks, Recreation and Historic Preservation.
In late 2006, NYPA completed a 15-year, $298
million upgrade of the Robert Moses Niagara Power Plant, the Niagara
project’s main generating facility. The work, intended to ensure
long-term efficient operation, entailed replacement of the turbines
and improvements to the generators and other components of each of
the plant’s 13 generating units. Extensive maintenance was also
completed in 2006 at the project’s Lewiston Pump-Generating Plant,
which supplements the Moses plant’s output at times of greatest use
of electricity.
The Power Authority is currently carrying out an
extensive refurbishing of the dam at the Moses plant.
Photos and Captions
About NYPA:
■ NYPA uses no tax money or
state credit. It finances its operations through the sale of
bonds and revenues earned in large part through sales of
electricity. ■ NYPA is a leader in promoting
energy-efficiency, new energy technologies and electric
transportation initiatives. ■ It is the
nation’s largest state-owned electric utility, with 18 generating
facilities in various parts of the state and more than 1,400
circuit-miles of transmission lines.
Return to Press Center
|