|
NYPA’s Blenheim-Gilboa Project Resumes Power
Production
Contact:
Steve Ramsey
518-287-6390
steve.ramsey@nypa.gov
November 15, 2006
FOR IMMEDIATE RELEASE
GILBOA—The New York Power Authority’s (NYPA)
Blenheim-Gilboa Pumped Storage Power Project has returned to service
after completing the first phase of a program to modernize the plant
and extend its life.
One of the project’s four pump-generating units
resumed production of electricity on Nov. 13 and two others are
expected to do so by Nov. 20. The fourth unit is scheduled to be
available by June 2007, on time to help meet power needs in the peak
summer period.
The shutdown of the entire project, which began
Sept. 23, was necessary because operators reduced the water levels
in the facility’s upper reservoir to permit replacement of a
spherical valve that controls the flow of water into the
powerhouse. The project’s three other spherical valves will be
refurbished in succeeding years, also requiring temporary shutdowns.
“Our workers at Blenheim-Gilboa have completed an
extraordinary undertaking in which the project was shut down and
returned to service in line with an extremely demanding schedule and
water management plan,” said Allen Schriver, NYPA’s regional manager
for Central New York. “This bodes well for the success of our
overall Life Extension and Modernization [LEM] program.”
Lynn Hait, maintenance resource management
superintendent/LEM site coordinator, said, “This accomplishment
became a reality through the superb efforts of a dedicated and
committed NYPA team.”
The four-year, $135 million Life Extension and
Modernization program is intended to ensure that the Blenheim-Gilboa
project operates at maximum efficiency for many years to come.
Work will include replacement of many of the major
mechanical and electrical components, and maintenance and repairs to
virtually all other parts. The work on the first unit is scheduled
for completion by next June, with the process to be repeated for the
others beginning in the fall of 2007, 2008 and 2009. The entire
program is to be completed in May 2010.
The 1,040,000-kilowatt Blenheim-Gilboa project,
which began operation in 1973, supplies electricity during periods
of greatest consumer demand. Water released from the upper
reservoir, atop Brown Mountain, plunges 1,042 feet within the
mountain to power the four turbine-generators, then flows into a
lower reservoir on Schoharie Creek. At night and on weekends, when
demand is lower, water is pumped back to the upper reservoir, using
economical electricity from other sources.
About NYPA:
■ NYPA uses no tax money or
state credit. It finances its operations through the sale of
bonds and revenues earned in large part through sales of
electricity. ■ NYPA is a leader in promoting
energy-efficiency, new energy technologies and electric
transportation initiatives. ■ It is the
nation’s largest state-owned electric utility, with 18 generating
facilities in various parts of the state and more than 1,400
circuit-miles of transmission lines.
Return to Press Center
|